Exploring effect of different resource qualities on process efficiency in construction pile installation

    Dominic Page Affiliation
    ; Lei Hou Affiliation
    ; Payam Rahnamayiezekavat Affiliation
    ; Maxwell Fordjour Antwi-Afari Affiliation
    ; SangHyeok Han Affiliation
    ; Sungkon Moon Affiliation

Abstract

This paper presents the measured effects of different resource qualities on construction performance. The paper describes a recommended method, proposed with the concept of prediction by understanding the causal effect of process resources on consequent work efficiencies. The project team measured and compared the different arrangements of resources and their effects on on-site work efficiencies. The paper includes a field study of 15 operations (40 piles) in Melbourne, on several worksites of prefabricated piles and installations. It aimed to determine the causality between the set of delivered prefabricated piles and relevant work efficiencies. This field includes its purpose of generating and providing scientific evidence in effectively implementing an offsite operation. One of the critical factors affecting the efficiency of the installation process was confirmed to be the location of the longest section in the sequence. It took 21.8 minutes longer with the middle part of the installation if the longest section was designed to be in the middle of the whole prefabricated steel pile. The findings confirmed the need for holistic communication along the supply chain. The originality of this project is to provide a case study that offers archival evidence of the proposed model in a practical situation.

Keyword : early supplier involvement, strategy development, distribution and logistics, offsite construction, work efficiency

How to Cite
Page, D., Hou, L., Rahnamayiezekavat, P., Antwi-Afari, M. F., Han, S., & Moon, S. (2023). Exploring effect of different resource qualities on process efficiency in construction pile installation. Journal of Civil Engineering and Management, 29(5), 463–474. https://doi.org/10.3846/jcem.2023.19215
Published in Issue
Jul 18, 2023
Abstract Views
831
PDF Downloads
378
Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

References

Abuhav, I. (2017). ISO 9001:2015 – A complete guide to quality management systems. CRC Press. https://doi.org/10.4324/9781315369808

Arif, M., & Egbu, C. (2010). Making a case for offsite construction in China. Engineering, Construction and Architectural Management, 17(6), 536–548. https://doi.org/10.1108/09699981011090170

Ashford, J. L. (2002). The management of quality in construction. CRC Press. https://doi.org/10.4324/9780203473153

Atherinis, D., Bakowski, B., Velcek, M., & Moon, S. (2017). Developing and laboratory testing a smart system for automated falsework inspection in construction. Journal of Construction Engineering and Management, 144(3), 04017119. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001439

Bernold, L. E., & AbouRizk, S. M. (2010). Managing performance in construction. John Wiley & Sons, Inc. https://doi.org/10.1002/9780470638996

Billodeau, C. (2010). Practice bulletin for upending rebar cages and/or peir columns. Brayman Construction.

Bishop, C. D., & Uriz, P. (2015). Column-Reinforcing cage stability and construction safety. In Seventh Congress on Forensic Engineering (pp. 318–327). ASCE. https://doi.org/10.1061/9780784479711.031

Bishop, C. D., Uriz, P., & McDonald, B. (2015). Stability of column rebar cages for buildings under construction. In Structural Stability Research Council Annual Stability Conference 2015 (SSRC 2015), Nashville, Tennessee, USA.

Builes-Mejia, J. C., Itani, A., & Sedarat, H. (2010). Stability of bridge rebar cages during construction (Report No. CCEER 10-07). Center for Civil Engineering Earthquake Research, USA.

Casey, M. J., & Urgessa, G. S. (2013). Temporary support for rebar column cages during construction. Practice Periodical on Structural Design and Construction, 18(3), 145–148. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000155

Chen, R., Tan, Y., Zhang, B., Shen, W., Liu, G., & Wang, Z. (2018). Installation of integral prefabricated bridge abutment and pier with flexible water stop curtain. Journal of Construction Engineering and Management, 144(9), 04018087. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001544

Chiheb, Z. (2017). Offsite construction is the future – ignore it at your peril. https://www.architectsjournal.co.uk/buildings/essay-offsite-construction-is-the-future-ignore-it-at-your-peril/10023964.article

Cooke, B., & Williams, P. (2013). Construction planning, programming and control. Wiley.

Davis, K., Ledbetter, W. B., & Burati Jr., J. L. (1989). Measuring design and construction quality costs. Journal of Construction Engineering and Management, 115(3), 385–400. https://doi.org/10.1061/(ASCE)0733-9364(1989)115:3(385)

Dettenmaier, P. (1997). Offsite construction. McGraw-Hill.

Durdyev, S., & Ismail, S. (2019). Offsite manufacturing in the construction industry for productivity improvement. Engineering Management Journal, 31(1), 35–46. https://doi.org/10.1080/10429247.2018.1522566

Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2011). BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors. Wiley.

Ellis Jr., R. D., & Lee, S. H. (2006). Measuring project level productivity on transportation projects. Journal of Construction Engineering and Management, 132(3), 314–320. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:3(314)

Emmitt, S. (2018). Barry’s advanced construction of buildings. Wiley.

Engineers Australia. (2020). Analysing the benefits of off-site construction. https://www.engineersaustralia.org.au/News/analysing-benefits-site-construction

Eze, E. C., & Idiake, J. E. (2018). Impact of rework on building project and organisation performance: A view of construction professionals in Nigeria. International Journal of Sustainable Construction Engineering and Technology, 9(1), 29–43. https://doi.org/10.30880/ijscet.2018.09.01.003

Ferguson, D. L. (2017). Removing the barriers to efficient manufacturing: Real-world applications of Lean productivity. Taylor & Francis. https://doi.org/10.1201/b13766

Fernald, D. H., Coombs, L., Dealleaume, L., West, D., & Parnes, B. (2012). An assessment of the Hawthorne effect in practice-based research. Journal of the American Board of Family Medicine, 25(1), 83–86. https://doi.org/10.3122/jabfm.2012.01.110019

Ferreras, A. M., & Crumpton-Young, L. L. (2017). Company success in manufacturing organizations: A holistic systems approach. CRC Press. https://doi.org/10.1201/9781315118314

Field, M., & Keller, L. S. (1998). Project management. International Thomson Business Press.

Gibb, A. G. F. (1999). Off-site fabrication: Prefabrication, pre-assembly and modularisation. John Wiley & Sons.

Gibb, A., & Isack, F., 2003. Re-engineering through pre-assembly: Client expectations and drivers. Building Research & Information, 31(2), 146–160. https://doi.org/10.1080/09613210302000

Gosling, J., Pero, M., Schoenwitz, M., Towill, D., & Cigolini, R. (2016). Defining and categorizing modules in building projects: An international perspective. Journal of Construction Engineering and Management, 142, 04016062. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001181

Goulding, J. S., & Rahimian, F. P. (2019). Offsite production and manufacturing for innovative construction: People, process and technology. CRC Press. https://doi.org/10.1201/9781315147321

Hairstans, R. (2010). Off-site and modern methods of timber construction: A sustainable approach. TRADA Technology Limited.

Han, S. H., Hasan, S., Bouferguène, A., Al-Hussein, M., & Kosa, J. (2015). Utilization of 3D visualization of mobile crane operations for modular construction on-site assembly. Journal of Management in Engineering, 31, 04014080. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000317

Hong, W. K. (2019). Hybrid composite precast systems: Numerical investigation to construction. Elsevier Science.

Hou, L., Tan, Y., Luo, W., Xu, S., Mao, C., & Moon, S. (2020). Towards a more extensive application of off-site construction: A technological review. International Journal of Construction Management, 22(11), 2154–2165. https://doi.org/10.1080/15623599.2020.1768463

Hou, L., Zhao, C., Wu, C., Moon, S., & Wang, X. (2017). Discrete firefly algorithm for scaffolding construction scheduling. Journal of Computing in Civil Engineering, 31, 04016064. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000639

International Federation for Structural Concrete (fib). (2002). Precast concrete in mixed construction: State-of-the-art report.

Kerzner, H. (2009). Project management: A systems approach to planning, scheduling, and controlling. Wiley.

Kim, K., Cho, Y. K., & Kim, K. (2018). BIM-based decision-making framework for scaffolding planning. Journal of Management in Engineering, 34, 04018046. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000656

Knaack, U., Chung-Klatte, S. & Hasselbach, R. (2012). Prefabricated systems: Principles of construction. Birkhäuser. https://doi.org/10.1515/9783034611404

Lawson, M., Ogden, R., & Goodier, C. (2014). Design in modular construction. Taylor & Francis. https://doi.org/10.1201/b16607

Lock, D. (2007). The essentials of project management. Gower.

Love, P. E. (2002). Auditing the indirect consequences of rework in construction: A case based approach. Managerial Auditing Journal, 17(3), 138–146. https://doi.org/10.1108/02686900210419921

Lu, N. (2009). The current use of offsite construction techniques in the United States construction industry. In Construction Research Congress 2009: Building a Sustainable Future (pp. 946–955). ASCE Press. https://doi.org/10.1061/41020(339)96

Luo, L., Jin, X., Shen, G. Q., Wang, Y., Liang, X., Li, X., & Li, C. Z. (2020). Supply chain management for prefabricated building projects in Hong Kong. Journal of Management in Engineering, 36, 05020001. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000739

Mahadevan, B. (2009). Operation management: Theory and practice. Pearson Education.

Mccabe, S. (2014). Quality improvement techniques in construction: Principles and methods. CRC Press. https://doi.org/10.4324/9781315840864

McKinsey Global Institute. (2017). Reinventing construction: A route to higher productivity. McKinsey & Company.

Metro Tunnel. (2018). Piling works at Parkville, Metro Tunnel. https://dokumen.tips/documents/piling-works-at-parkville-metro-tunnel-the-use-of-heavy-machinery-such-as-piling.html?page=1

Moon, S., Zekavat, P. R., & Bernold, L. E. (2015). Dynamic control of construction supply chain to improve labor performance. Journal of Construction Engineering and Management, 141, 05015002. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000970

Moon, S., Forlani, J., Wang, X., & Tam, V. (2016). Productivity study of the scaffolding operations in liquefied natural gas plant construction: Ichthys Project in Darwin, Northern territory, Australia. Journal of Professional Issues in Engineering Education and Practice, 142, 04016008. https://doi.org/10.1061/(ASCE)EI.1943-5541.0000287

Moon, S., Zekavat, P. R., Bernold, L. E., & Leviakangas, P. (2018). Dynamic control of resource logistics quality to eliminate process waste in rebar placement work. KSCE Journal of Civil Engineering, 22, 3697–3706. https://doi.org/10.1007/s12205-018-1883-8

Moon, S., Ham, N., Kim, S., Hou, L., Kim, J. H., & Kim, J. J. (2020). Fourth industrialization-oriented offsite construction: case study of an application to an irregular commercial building. Engineering, Construction and Architectural Management, 27(9), 2271–2286. https://doi.org/10.1108/ECAM-07-2018-0312

Mukherjee, P. N. (2006). Total quality management. PHI Learning.

Nawy, E. G. (2008). Concrete construction engineering handbook. CRC Press. https://doi.org/10.1201/9781420007657

ReVelle, J. B. (2016). Manufacturing handbook of best practices: An innovation, productivity, and quality focus. CRC Press.

Smith, R. E., & Quale, J. D. (2017). Offsite architecture: Constructing the future. Taylor & Francis. https://doi.org/10.4324/9781315743332

Smith, R. E., & Timberlake, J. (2011). Prefab architecture: A guide to modular design and construction. Wiley.

Temporary Works Forum. (2013). Stability of reinforcement cages prior to concreting (No. TWf2013:01). http://www.twforum.org.uk

Thomas, H. R., Minchin Jr., R. E., & Chen, D. (2003). Role of workforce management in bridge superstructure labor productivity. Journal of Management in Engineering, 19(1), 9–16. https://doi.org/10.1061/(ASCE)0742-597X(2003)19:1(9)

Urgessa, G. S., Lattanzi, D., & Casey, M. J. (2016). Stability of large reinforcing column cages during temporary construction conditions. Practice Periodical on Structural Design and Construction, 21(1), 04015003. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000259

Yu, H., Al-Hussein, M., Al-Jibouri, S., & Telyas, A. (2013). Lean transformation in a modular building company: A case for implementation. Journal of Management in Engineering, 29, 103–111. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000115

Zayed, T. M., & Halpin, D. W. (2004). Process versus data oriented techniques in pile construction productivity assessment. Journal of Construction Engineering and Management, 130(4), 490–499. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:4(490)